October 28, 2026
Lahaina, HI – Oct. 19-23, 2026
At the Walker house, five or six volunteers worked on finishing up framing early in the week. Truss “tails” were trimmed, and a lot of metal bracing was installed. Because of the way soffits are installed in Hawaii, “bird blocks” are part of early construction. Picture a short 2 x 4 with 3 large holes drilled, then covered with wire mesh, to keep birds out of the attic. The space between each truss needs a bird block. It was a real sign of progress when volunteers could begin roof sheeting later in the week. Mrs. Walker brought ice cream treats one day, and then on Friday she brought lunch for the crew.
Work slowed somewhat at the Hashimura house, as we must wait for the plumber and electrician to complete their work before it’s inspected and insulating can begin. Siding is being installed, and two doors were placed. On Friday the kitchen window was installed, a special order that finally arrived midweek.
Work at the Madrigal house was all about drywall. Sanding, and more sanding. And then some more sanding! As one volunteer aptly stated, there are seven bedrooms, four baths, two kitchens, two living rooms, two carports, and about 100 closets (for a multigenerational family of eleven). Well, we admit there aren’t actually 100 closets, but mudding and sanding all those corners was time consuming, to say the least! By week’s end most of the priming was complete, and a finish coat actually graced a few walls!
Another crew worked on the ceilings in the carport and began wrapping the posts on the lanais. The lot looked so much nicer after a large load of trash and construction debris was loaded and hauled away later in the week.
A real highlight was the Wednesday evening meal with local Rotary Club representatives, as well as the two women who had taught us how to make leis earlier. After a fruitful time of learning from and about each other, we were honored honored with a hula exhibition.
On Friday evening, we said goodbye to the three yearlong volunteers, who had been with us since the project opened in September. They were such assets to the work here, and we wish them all the very very best as they continue their time with MDS in a variety of other projects throughout the coming year. We also bid farewell to the construction supervisor and his spouse, who served as “production support,” AKA “go-fer.” They will be missed as we adjust to life in Lahaina without them.
And, of course, we said goodbye to the team of weekly volunteers, each of whom added their own particular “flavor” to our mix of willing workers. We look forward to a new group with anticipation. In addition, a new construction supervisor and crew leader are present. We continue to press forward, working to return people home.